Contractor picked for earthquake-damaged Washington Monument

Perini Management Services Inc. of Framingham, Mass., beat out two other bidders to win a $9.6 million contract to repair earthquake damage to the Washington Monument. The marble and granite obelisk has been closed to the public since an earthquake shook the region in 2011.

American flags fly below the Washington Monument, Wednesday, Wednesday, in Washington. The Washington Monument was damaged and has been closed to visitors since the August 2011 earthquake.

Alex Brandon/AP

September 26, 2012

The National Park Service named a Massachusetts contractor Wednesday to repair the Washington Monument's earthquake damage, though it may take two more months before work begins at the National Mall site.

Perini Management Services Inc. of Framingham, Mass., beat out two other bidders to win a $9.6 million contract that includes extensive repairs to the monument's stonework. It will involve building massive scaffolding around the 555-foot-tall monument, sealing cracks inside and out, repointing the mortar, cleaning the exterior and strengthening weak spots with metal brackets. The total cost of repairs, including work already completed, is $15 million.

Federal officials said the contractor's parent company was the prime contractor for the construction of the Ronald Reagan Building, Washington's largest federal building. The contractor's team also includes firms involved in a restoration of the monument completed in 2000.

In Kentucky, the oldest Black independent library is still making history

"We are again one step closer to getting this important landmark reopened to our visitors," said Robert Vogel, superintendent of the National Mall and Memorial Parks.

The marble and granite obelisk has been closed to the public since a 5.8-magnitude earthquake shook the region on Aug. 23, 2011. The upper portion of the monument sustained large cracks when it shook violently during the quake. It will likely remain closed to visitors until 2014.

Park service project manager Michael Morelli said gaining access to the tall monument is the most difficult portion of the project.

"The actual repairs to the monument are actually the easiest portion of the work," he said.

Within about 60 days, work will begin at the site to begin building the scaffolding. That alone will take four to five months, said Brian Labbe, who will serve as construction manager for Perini Management. Scaffolding will likely be built inside the monument's top pyramidion, where some of the worst damage was found.

A majority of Americans no longer trust the Supreme Court. Can it rebuild?

Once work begins, the project will take 12 to 18 months to complete, officials said.

Congress allocated $7.5 million to pay for repairs. In January, Washington businessman David Rubenstein pledged another $7.5 million.

The monument was completed in 1884 and was the world's tallest structure until 1889, when the Eiffel Tower was built. Vogel said it remains the tallest freestanding stone structure in the world.

"The monument," he said, "is one of a kind."