Two weeks till the Olympics, and still a long to-do list

It's time to put on the finishing touches on Olympic Park; will it be a mad rush to finish before the opening ceremony?

(Page 2 of 2)



"This is all cosmetic stuff," he said. "Look! There are some flowers growing over there!"

Skip to next paragraph

Bulley said the venues, after the construction and fit-out phases, are now in their final "bump-in" period. Television networks from around the world are moving in and cabling the venues for their cameras. LOCOG's "look'" teams are completing the signage and color schemes. Sports equipment is being shipped in.

"We're still putting in seats at probably 10 or so venues," Bulley said. "We're putting in 1,000 seats a day."

The "live site" in the Olympic Park — a grassy area where spectators can watch the events on a giant screen and listen to musical entertainment — is also unfinished.

"The bump-in looks quite messy, but you leave this to the last stages," Bulley said. "It's always the last thing you do in getting events ready. We want to work these venues right up to when the athletes are coming in so they look as good as possible."

Olympic Park isn't the only place getting dolled up.

So is Horse Guards Parade, the ceremonial parade ground a stone's throw from the Prime Minister's Downing Street residence in central London, and site of beach volleyball. It's a temporary venue which requires stands and 5,000 tons of sand brought in from a quarry south of London. Imagine a giant sandbox. Work started only late last month after the Trooping of the Color ceremony marking Queen Elizabeth II's birthday.

Another key venue requiring special attention is ExCel. The conference and exhibition center in the Docklands area is being turned into multiple arenas hosting boxing, judo, table tennis, wrestling, fencing, taekwondo and weightlifting.

"We're well advanced," Bulley said. "We'll be ready to hand those arenas over as of early next week. We took the venues later than many of the others. We've always known the period we've had to deliver these venues. We track them very closely. We're in super shape."

International Olympic Committee President Jacques Rogge said it's normal for host cities to face a flurry of last-ditch issues.

"It's not peculiar for London," he said. "We've always had difficulties in the days leading up to the games in the previous games and the games were of an impeccable nature. This is something that does not worry us. We're confident that everything will be fine by the opening ceremony day."

Even Andrew Boff, a member of the London Assembly and vocal critic of the Olympic project, has no doubts.

"It's the nature of any games," he said. "They look unfinished before you get there. But the venues are ready. They've been tested. You can do a lot in 12 days. If it weren't ready, Seb Coe would have his Lordship or knighthood taken away."

Associated Press Writer Danica Kirka and AP Sports Writer Chris Lehourites contributed to this report.

Read Comments

View reader comments | Comment on this story

  • Weekly review of global news and ideas
  • Balanced, insightful and trustworthy
  • Subscribe in print or digital

Special Offer

 

Doing Good

 

What happens when ordinary people decide to pay it forward? Extraordinary change...

Danny Bent poses at the starting line of the Boston Marathon in Hopkinton, Mass.

After the Boston Marathon bombings, Danny Bent took on a cross-country challenge

The athlete-adventurer co-founded a relay run called One Run for Boston that started in Los Angeles and ended at the marathon finish line to raise funds for victims.

 
 
Become a fan! Follow us! Google+ YouTube See our feeds!